Water treatment plant upgrade on track

3 minutes read
Posted 14 November, 2023
Two Mile web

Two Mile water treatment plant

Work to install protozoa barriers across the district is progressing well, says council infrastructure boss Tony Avery.

Queenstown Lakes District Council (QLDC) has been working at pace to install UV treatment at its Two Mile water treatment plant, in tandem with similar plants in the district that currently do not have such systems in place to protect against protozoa such as cryptosporidium.

Work to design, procure, obtain consent for and commission a protozoa barrier at Two Mile has been ongoing since national water regulator Taumata Arowai issued Council with a compliance order on 20 September following a local outbreak of illness caused by cryptosporidium.

QLDC General Manager Property & Infrastructure Tony Avery says installing the barrier itself was only one part of the overall project.

"We’ll also be cleaning and flushing the entire network supplied by Two Mile. This is a significant, one-off undertaking outside of normal business and something we’ve been planning alongside work at the treatment plant itself," he says.

"It will include draining and cleaning Fernhill #1 Reservoir as well as cleaning and inspecting all other network reservoirs. We’ll also be flushing the piped network to ensure any sediment where cryptosporidium could potentially still reside is displaced.

"Whilst the possibility of contamination during these activities is low and extreme care will be taken, they do introduce some additional risk. It’s still really important that people in affected areas keep boiling their water.

"In addition, we ask that everyone including commuters and visitors from other parts of the district maintain good personal hygiene – specifically cleaning and drying their hands thoroughly – to help ensure we stamp out the risk of further cases in our community."

Avery says a site office was established some weeks ago near Fernhill Reservoir and the container that will hold the UV system is already on-site at the Two Mile plant.

"This will be a temporary system that, along with successful cleaning and flushing, will meet all requirements of the compliance order in the fastest possible time.

"It will be transferred to another of our treatment plants once a permanent system is completed at Two Mile. We’ve been designing systems for other plants in parallel in order to achieve full compliance across the district as quickly as possible."

Avery says the project remains on track to its original estimated completion date of 8 December.

"Whilst the date when the current boil water notice can be lifted ultimately depends on approval by Taumata Arowai, we continue to work positively with the regulator to ensure residents, visitors and businesses in affected parts of Queenstown can return to normal water usage as soon as possible, targeting the week of 11 December.

"We have also been planning preparation work for the Western Wānaka water intake which will begin this week and include a temporary realignment of the lakeside Millennium Track. We’ll be working with Te Kākano to reinstate and hopefully expand any areas of native planting affected by this work.

"There is currently no need for people in the Upper Clutha, Frankton or other neighbourhoods outside the current area under the notice to boil water.

"This continues to be a major project for Council’s infrastructure, legal and planning staff as well as contractors Fulton Hogan and Veolia. They are completing work in weeks that would typically take many months. We also continue to acknowledge the patience and resilience being shown by individuals and businesses in the affected areas.”

A public health investigation led by Te Whatu Ora Health New Zealand concluded on 6 October that human faecal contamination of the water supply as the most likely source.

Te Whatu Ora confirmed that from the start of the outbreak until 7 November there have been 72 confirmed cases of cryptosporidiosis (the illness caused by cryptosporidium), 20 probable cases and two that remain under investigation.

A boil water notice remains in the following areas:

Queenstown town centre

Gorge Rd out to and including Industrial Place

Fernhill

Sunshine Bay

Queenstown Hill above Frankton Rd out to and including Goldridge Way and Goldrush Way

 

QLDC water schemes/ distribution zones currently without a protozoa barrier:

Queenstown (Two Mile)

Wānaka

Luggate

Glenorchy

Wānaka Airport

Corbridge 

Schemes/distribution zones with a protozoa barrier:

Arrowtown

Arthurs Point

Kelvin Heights (including Frankton, Hanley’s Farm, Quail Rise and Tucker Beach Rd)

Lake Hayes, Lakes Hayes Estate, Shotover Country

Lake Hāwea

 

(QLDC does not supply water to Kingston)

Screenshot 2023 11 14 142019

Advert
Advert
SHARE ON

Related articles

Latest issue

Issue 987 Read Now

Last week’s issue

Issue 986 Read Now

DISCOVER THE QUEENSTOWN APP

Download or update to the new Queenstown App today

image

WHY ADVERTISE YOUR BUSINESS WITH US

The Lakes Weekly is part of Queenstown Media Group (QMG).

QMG is Queenstown’s leading locally owned and operated media company with print, online and social platforms that engage locals with what they care about — everything local!

The Lakes Weekly delivers stories and news that connects with local so they come away each week better connected to their community. Advertising sits within this curated content environment, and it’s a trusted relationship between readers and the Lakes Weekly. Advertisers benefit from the association with the LWB brand values.

The Lakes Weekly is hand delivered to every business in Queenstown, Arrowtown, Frankton, Five Mile Remarkables Park and Glenda Drive on Tuesday. Copies are available in service stations, libraries and drop boxes throughout the region and every supermarket throughout the Queenstown basin and Wanaka.

Online the issue is available Monday afternoon, on lwb.co.nz and the Qtn App.

3,500

Printed copies
each week

13,250

Estimated weekly
readership
Read the
Latest issue